Reference 105316/HYB/21
Alternative Reference PP-10034385
Application Received Tue 20 Jul 2021
Application Validated Tue 20 Jul 2021
Address Power Station 132 Manchester Road Carrington M31 4AY
Proposal Hybrid application comprising: (a) Full application for the creation of a green hydrogen production facility (10MW capacity, circa 4 tonnes of hydrogen production per day), including battery storage, compressors, hydrogen storage and tanker loading facilities. (b) Outline application with all matters reserved for an expanded green hydrogen production facility within wider site (200MW capacity, up to 50 tonnes of hydrogen storage).
Status Decided
Decision Approve with Conditions
Decision Issued Date Thu 29 Sep 2022
Appeal Status Unknown
Appeal Decision Not Available

Further Information

Application Type Hybrid App (Part Full & Part Outline)
Decision Approve with Conditions
Actual Decision Level Delegated Decision
Expected Decision Level Not Available
Case Officer Jeff Davis
Parish Carrington Parish Council
Ward Bucklow St Martins
District Reference Not Available
Applicant Name Mr Eric Adams
Applicant Address 26 Ellerbeck Court Stokesley TS9 5PT United Kingdom
Environmental Assessment Requested No

Contacts

There are no contacts associated with this case.

Important Dates

Application Received Date Tue 20 Jul 2021
Application Validated Date Tue 20 Jul 2021
Expiry Date Thu 16 Sep 2021
Actual Committee Date Not Available
Latest Neighbour Consultation Date Mon 09 Aug 2021
Neighbour Consultation Expiry Date Mon 30 Aug 2021
Standard Consultation Date Wed 25 Aug 2021
Standard Consultation Expiry Date Wed 15 Sep 2021
Last Advertised In Press Date Not Available
Latest Advertisement Expiry Date Not Available
Last Site Notice Posted Date Thu 26 Aug 2021
Latest Site Notice Expiry Date Thu 16 Sep 2021
Agreed Expiry Date Fri 30 Sep 2022
Decision Made Date Thu 29 Sep 2022
Decision Issued Date Thu 29 Sep 2022
Permission Expiry Date Wed 29 Sep 2027
Decision Printed Date Thu 29 Sep 2022
Environmental Impact Assessment Received Not Available
Determination Deadline Tue 19 Oct 2021
Temporary Permission Expiry Date Not Available

Constraints

Name Constraint Type Status
Landscape Improvement Areas - ENV20 Landscape Improvement Not Available
Manchester Intl Airport - All development exceeding 90 metre Airport Consultation Zone Not Available
EA Flood Risk Zone 2 Not Available Not Available
Smoke Control Zone Smoke Control Zone Not Available
Special Landscape Features - ENV18 UDP Policies Not Available
Main employment Areas - E7 UDP Policies Not Available
Priority Regeneration Area (Carrington) - E15 UDP Policies Not Available
Sites for Reclamation - ENV32 UDP Policies Not Available
River Valley Flood Risk - ENV13 UDP Policies Not Available
Community Forest / Tree Planting - ENV15/ENV16 UDP Policies Not Available
Main Industrial Areas - E7 UDP Policies Not Available
Borough Wide-HMO Art 4 Direction 2015. Effective 21/12/2017 Article 4 Direction Active