Reference | 105316/HYB/21 |
---|---|
Alternative Reference | PP-10034385 |
Application Received | Tue 20 Jul 2021 |
Application Validated | Tue 20 Jul 2021 |
Address | Power Station 132 Manchester Road Carrington M31 4AY |
Proposal | Hybrid application comprising: (a) Full application for the creation of a green hydrogen production facility (10MW capacity, circa 4 tonnes of hydrogen production per day), including battery storage, compressors, hydrogen storage and tanker loading facilities. (b) Outline application with all matters reserved for an expanded green hydrogen production facility within wider site (200MW capacity, up to 50 tonnes of hydrogen storage). |
Status | Decided |
Decision | Approve with Conditions |
Decision Issued Date | Thu 29 Sep 2022 |
Appeal Status | Unknown |
Appeal Decision | Not Available |
Application Type | Hybrid App (Part Full & Part Outline) |
---|---|
Decision | Approve with Conditions |
Actual Decision Level | Delegated Decision |
Expected Decision Level | Not Available |
Case Officer | Jeff Davis |
Parish | Carrington Parish Council |
Ward | Bucklow St Martins |
District Reference | Not Available |
Applicant Name | Mr Eric Adams |
Applicant Address | 26 Ellerbeck Court Stokesley TS9 5PT United Kingdom |
Environmental Assessment Requested | No |
There are no contacts associated with this case.
Application Received Date | Tue 20 Jul 2021 |
---|---|
Application Validated Date | Tue 20 Jul 2021 |
Expiry Date | Thu 16 Sep 2021 |
Actual Committee Date | Not Available |
Latest Neighbour Consultation Date | Mon 09 Aug 2021 |
Neighbour Consultation Expiry Date | Mon 30 Aug 2021 |
Standard Consultation Date | Wed 25 Aug 2021 |
Standard Consultation Expiry Date | Wed 15 Sep 2021 |
Last Advertised In Press Date | Not Available |
Latest Advertisement Expiry Date | Not Available |
Last Site Notice Posted Date | Thu 26 Aug 2021 |
Latest Site Notice Expiry Date | Thu 16 Sep 2021 |
Agreed Expiry Date | Fri 30 Sep 2022 |
Decision Made Date | Thu 29 Sep 2022 |
Decision Issued Date | Thu 29 Sep 2022 |
Permission Expiry Date | Wed 29 Sep 2027 |
Decision Printed Date | Thu 29 Sep 2022 |
Environmental Impact Assessment Received | Not Available |
Determination Deadline | Tue 19 Oct 2021 |
Temporary Permission Expiry Date | Not Available |
Name | Constraint Type | Status |
---|---|---|
Landscape Improvement Areas - ENV20 | Landscape Improvement | Not Available |
Manchester Intl Airport - All development exceeding 90 metre | Airport Consultation Zone | Not Available |
EA Flood Risk Zone 2 | Not Available | Not Available |
Smoke Control Zone | Smoke Control Zone | Not Available |
Special Landscape Features - ENV18 | UDP Policies | Not Available |
Main employment Areas - E7 | UDP Policies | Not Available |
Priority Regeneration Area (Carrington) - E15 | UDP Policies | Not Available |
Sites for Reclamation - ENV32 | UDP Policies | Not Available |
River Valley Flood Risk - ENV13 | UDP Policies | Not Available |
Community Forest / Tree Planting - ENV15/ENV16 | UDP Policies | Not Available |
Main Industrial Areas - E7 | UDP Policies | Not Available |
Borough Wide-HMO Art 4 Direction 2015. Effective 21/12/2017 | Article 4 Direction | Active |
There are 39 documents associated with this application.
There are 0 cases associated with this application.
There is 1 property associated with this application.