Skip to main content

Planning – Application Dates

Help with this page (opens in a new window)

105316/HYB/21 | Hybrid application comprising: (a) Full application for the creation of a green hydrogen production facility (10MW capacity, circa 4 tonnes of hydrogen production per day), including battery storage, compressors, hydrogen storage and tanker loading facilities. (b) Outline application with all matters reserved for an expanded green hydrogen production facility within wider site (200MW capacity, up to 50 tonnes of hydrogen storage). | Power Station 132 Manchester Road Carrington M31 4AY
Application Received Date Tue 20 Jul 2021
Application Validated Date Tue 20 Jul 2021
Expiry Date Thu 16 Sep 2021
Actual Committee Date Not Available
Latest Neighbour Consultation Date Mon 09 Aug 2021
Neighbour Consultation Expiry Date Mon 30 Aug 2021
Standard Consultation Date Wed 25 Aug 2021
Standard Consultation Expiry Date Wed 15 Sep 2021
Last Advertised In Press Date Not Available
Latest Advertisement Expiry Date Not Available
Last Site Notice Posted Date Thu 26 Aug 2021
Latest Site Notice Expiry Date Thu 16 Sep 2021
Agreed Expiry Date Fri 30 Sep 2022
Decision Made Date Thu 29 Sep 2022
Decision Issued Date Thu 29 Sep 2022
Permission Expiry Date Wed 29 Sep 2027
Decision Printed Date Thu 29 Sep 2022
Environmental Impact Assessment Received Not Available
Determination Deadline Tue 19 Oct 2021
Temporary Permission Expiry Date Not Available

an Idox solution

A to Z of Council Services