88589/FUL/16
|
Construction of new pedestrian and cycle bridge, with ramps, crossing the Bridgewater Canal to the east of Viaduct Road along with the formation of a new canal towpath, approximately 250m long, along the south side of the canal from the new bridge to Wharf Road. Associated construction accesses and temporary footpath diversion.
|
Land East Of Viaduct Road Altrincham
Application Received Date | Wed 01 Jun 2016 |
---|---|
Application Validated Date | Wed 01 Jun 2016 |
Expiry Date | Thu 04 Aug 2016 |
Actual Committee Date | Thu 11 Aug 2016 |
Latest Neighbour Consultation Date | Thu 21 Jul 2016 |
Neighbour Consultation Expiry Date | Thu 04 Aug 2016 |
Standard Consultation Date | Thu 21 Jul 2016 |
Standard Consultation Expiry Date | Thu 04 Aug 2016 |
Last Advertised In Press Date | Wed 29 Jun 2016 |
Latest Advertisement Expiry Date | Wed 20 Jul 2016 |
Last Site Notice Posted Date | Tue 12 Jul 2016 |
Latest Site Notice Expiry Date | Tue 02 Aug 2016 |
Agreed Expiry Date | Not Available |
Decision Made Date | Mon 15 Aug 2016 |
Decision Issued Date | Mon 15 Aug 2016 |
Permission Expiry Date | Thu 15 Aug 2019 |
Decision Printed Date | Mon 15 Aug 2016 |
Environmental Impact Assessment Received | Not Available |
Determination Deadline | Wed 31 Aug 2016 |
Temporary Permission Expiry Date | Not Available |